Starting Friday morning September 9, Platform B (Tracks 4 and 5) will no longer be accessible from the overpass leading to/from the Haven Avenue parking lot. Customers who need to access those tracks must walk to the station plaza. Access from the Haven Avenue parking lot to Platform A (Tracks 2 and 3) remains unaffected.
In order to accommodate the crane and other equipment required to accomplish the demolition work, part of the South Bayles Avenue parking lot will be closed for 24 hours, beginning at 8 p.m. on Friday night, September 9 and ending at 8 p.m. on Saturday night, September 10. All cars must be removed from the lot by 8 p.m. on Friday. Demolition will be completed Saturday night, and the parking lot will be restored for customer use by Sunday morning.
Installation of a new prefabricated pedestrian bridge is tentatively scheduled for mid to late October.